Engineering the Olympic Stadium

Document type: | Last updated: 10 JULY 2012

Hear from those who led the design and delivery of the Olympic Stadium. An innovative use of permanent and temporary forms was developed to meet the 80 000 games capacity and 25 000 legacy capacity, with the final structuring consisting of a permanent sunken concrete bowl and a removable upper seating tier. To save space and drive efficiencies, the majority of spectator facilities were moved outside the structure and the upper seating tier rakes outwards, resulting in the lightest stadium of its size in the world.

The rapid delivery of the stadium in just 34 months was achieved through a strategy of prefabrication of concrete and steel elements and just-in-time delivery, supported by a strong collaborative team-working ethic.

For more information, please contact (recordedlectures@ice.org.uk)

Visit link

Get Acrobat Reader