Event archive

Event Organiser: ICE

QE2 bridge joint replacement, Ipswich

  • Lecture
  • 16 November 2016
  • 18:30 - 23:59
QE2 bridge joint replacement, Ipswich

Watch this event

The QEII bridge joint replacement project involved replacing 6 worn out bridge joints without disrupting traffic flows over the bridge.

This was achieved by utilising a temporary ramp system that allowed work to the joint replacement operations to continue with traffic running uninterrupted. The operation to install the temporary ramp had to be completed in a single shift overnight (Sat/Sun) so that the bridge was fully open by 10.00am on Sunday morning.

Extensive trails were conducted off-site, with the outputs being recorded and assessing/quantifying the risks using @Risk to provide HE with a Quantified Risk Assessment (QRA) from which a 14 hour closure was then granted.

In Phase 1, 160 shifts were undertaken and not one overran!

Speaker: Jon Cass – Contracts Manager Jackson Civils Ltd.

Contact

For more information, please contact:

Stephen Christian
e: schristian@jackson-civils.co.uk

Event venue

One Group Construction
30 White House
Ipswich
IP6 9LG
United Kingdom

For more information please contact:

Heather Bell

e: heather.bell@ice.org.uk
t:

Top