A diver-under structure was required to take two railway lines beneath the East Coast
Main Line, removing a key bottleneck on the network. A 150m long, 8m high, 11.5m
wide, 750m radius curved reinforced concrete box weighing 11,000T was constructed
offline and then jacked 165m into position during a 9-day partial closure of the main
line.
In this lecture, Matt Hadden will discuss the engineering challenges faced in the
construction of the scheme.
More like this

- Type
- Webinar
Careers talks
Aimed at students, this series of seven webinars which runs until May 2025 will enable you to learn about professional life from recent graduates from across the industry.


- Type
- Webinar
ICE Malaysia membership information session
This session aims to provide guidance on ICE membership pathways, categories, and the registration process. It is designed to help aspiring new members understand the benefits of joining the Institution of Civil Engineers (ICE).