- Date
- 18 March 2021
- Time
This event has now ended
Overview
A diver-under structure was required to take two railway lines beneath the East Coast
Main Line, removing a key bottleneck on the network. A 150m long, 8m high, 11.5m
wide, 750m radius curved reinforced concrete box weighing 11,000T was constructed
offline and then jacked 165m into position during a 9-day partial closure of the main
line.
In this lecture, Matt Hadden will discuss the engineering challenges faced in the
construction of the scheme.
More like this

- Type
- Webinar
Careers talks
Aimed at students, this series of seven webinars which runs until May 2025 will enable you to learn about professional life from recent graduates from across the industry.

- Type
- Webinar
5-week course: health and safety
A five session course delivered by industry experts to develop in-depth knowledge of health, safety, and wellbeing in civil engineering within the UK.

- Type
- Webinar
CEng communication task group: safety and health assessment system in construction (SHASSIC)
This event guides ICE Graduate members (GMICE) on the Safety and Health Assessment System in Construction (SHASSIC), providing expert insights into evaluating and improving safety and health in construction through assessments, risk controls, and performance benchmarks.