EKFB’s HS2 scope includes three Green Tunnels, which presented significant construction challenges. By 2024, progress on the tunnels was placing delivery of a critical project test length at risk.
The G2S Tunnel Team identified and implemented a series of strategic improvements to recover programme performance. Central to this approach was increased offsite prefabrication and manufacturing, combined with installation methods that maintained tunnel access and prioritised critical-path activities.
These changes accelerated delivery while enhancing efficiency. Additional benefits included improved quality control, reduced costs, and stronger safety performance.
In their presentation, Alexei & Christopher will outline the challenges faced and the key innovations implemented, including the transition to prefabricated invert slab reinforcement, shortlisted for the NCE Tunnelling Awards in the category of Innovation in Construction Execution & Supply Chain Collaboration.
Following the presentation, there will be a networking session in the ICE Kendal's bar.
The BTS is a dynamic group of tunnelling professionals sharing knowledge within the industry.
EKFB (Kier)
G2S Project Director
Alexei joined EKFB as G2S Project Director in 2024, leading the delivery of a 25km section of the HS2 alignment, including 5.2km of Green Tunnel, 16.5 million m³ of earthworks and 21 bridge structures. Previously, on Tideway West, he managed the delivery of Carnwath Road and Main Tunnel A before being promoted to Project Director, with responsibility for the completion, testing, commissioning and handover of all seven project sites.
During his tenure, he led a major redesign of key civil works that delivered a six-month programme saving on an 18-month construction programme, demonstrating a strong track record in leading complex infrastructure projects and driving programme performance.
EKFB (BAM)
G2S Green Tunnel Senior Project Manager
Chris has been a key member of the BAM Tunnelling team since joining in 2010 and is currently Senior Project Manager for the Chipping Warden and Greatworth Green Tunnels on EKFB’s HS2 G2S project.
Over his career, he has led the delivery of several complex tunnelling schemes, including the design and construction of the Silvertown Tunnel cross passages, incorporating extensive ground-freezing operations; the Tunnel B Connection on Tideway West, a critical interface between project contracts; and the Carnwath Road Shaft, a 40m-deep, 26m-diameter structure forming a key component of the Tideway Tunnel project.

A useful five session course delivered by industry experts focussing on key aspects of finance in Civil Engineering.

Receive detailed and personalised guidance about the Fellowship process from ICE Scotland regional director, Matt Lancashire.

The talk will focus on how collaboration and empathy can help a structural engineer to contribute to projects that can make people smile.